Dredging on - Hindustan Times
In spite of the protests, and the breakdown of vessels active in the Ramar Setu area, the dredging of the canal has been going on. In the Palk Bay 1 area of the project, 13.44 million cubic feet (mcft) of sand has been dredged against the target of 13.55 mcft. Near Adam’s Bridge, 0.37 mcft of the targeted 4.80 mcft has been dredged.